Business Development Initiative for Success

Assuming that a business productivity project was done for a company, it would be first presented to the consulting company for approval before sending it to the prospective client for review. This project focused on a business development initiative that established the stages, which a prospective business person or entity should consider when developing a better strategy for the success of the company (Schmidt, 2009). In addition, it was developed to provide a prospective client with a clear overview of the proposed project so that he or she could determine whether to proceed with the project (Schmidt, 2009).

Table 1: Durations for Each Activity.

Task Predecessor Normal Time Crash Time Crash Cost Slope
A None 3 3 NA
B A 2 2 NA
C A 6 2 $600
D A 5 5 NA
E B 3 1 $600
F C 2 2 NA
G D 7 3 $600
H F, G 4 4 NA
I E 5 5 NA
J H 4 4 NA
K I, J 7 7 NA

Project Timeline under Normal Circumstances

Task Start Date # Days Required End Date
A 4/3/12 3 4/5/12
B 4/6/12 2 4/7/12
C 4/6/12 6 4/11/12
D 4/6/12 5 4/10/12
E 4/8/12 3 4/10/12
F 4/12/12 2 4/13/12
G 4/11/12 7 4/17/12
H 4/18/12 4 4/21/12
I 4/11/12 5 4/15/12
J 4/22/12 4 4/25/12
K 4/26/12 7 5/2/12
The Activity on Node (AON) Using Microsoft Project.
Figure 1: The Activity on Node (AON) Using Microsoft Project.

A Critical Path Analysis for the Network

Assuming that the project started on 4/3/12, crashing some tasks during the implementation did not change the length of time the, but only alter the time those activities took to end. For instance, crashing task C for 2 days only made it end on the same day with task B. This could not affect task D since B, C and D can run concurrently after Activity A is complete. However, crashing task G affected the end of activity J by reducing its termination.

Consequently, this affected the start and end of activity K, a situation that reduced the project duration by 4 days. Instead of the project ending on 05/02/2012, crashing of task G made it end on 04/28/2012. Therefore, crashing some project activities could only be done after carefully considering the impacts and benefits of such action. Only profitable actions could be exercised on the entire implementation of the project.

The Earliest Start Time = EST of previous activity + Duration of previous activity = 0+ 3 = 3

Earliest Finish Time (EFT) (A) = EFT at end of following activity – Duration of following activity = 5 – 3 = 3

Latest Start Time (LST) = LST of previous activity + Duration of previous activity (A) = 0 + 3 = 3

Latest Finish Time (LFT) Time (A) = LFT at end of following activity – Duration of following activity = 5 – 2 =3

Notably, the calculated values for EST, EFT, LST, and LFT are always equal. This indicates that there is minimal impact of changing the project timeframe on the quality of its outcome.

The Slack Time for Each Activity = Latest Start Time – Earliest Start Time

  • A = 3 – 0 = 3
  • B = 4 – 3 =1
  • C = 4 – 3 = 1
  • D = 4 – 3 = 1
  • E = 6 – 5 = 1
  • F = 10 – 2 = 8
  • G = 9 – 8 = 1
  • H = 16 – 3 = 13
  • I = 19 – 1 = 18
  • J = 20 – 21 = 1
  • K = 24 – 23 = 1

Identify the Critical Path

In this project, the critical path is A C F G H J K. this path is considered critical because Activity C can only commence after A is complete, F comes after C, G starts after F, H begins after G, J starts after H, and K only commences after J is complete.

Assuming that the organization will receive a $1,000 bonus for each day the duration of the project is shortened. Secondly, the organization is also responsible for paying the crash cost associated with shortening the schedule. Therefore, to maximize the net profit, the task that should be crashed is G. This activity will be crashed by 4 days, meaning that the company will receive 4 x $1,000 = $4,000. Alternatively, the crash cost for this activity will be 4 x $600 = $2,400. The profit will be $4,000 – $2,400 = $1,600.

The project aims to make the implementing organisation improve the overall productivity. The main objectives of the project included various elements. First, it aimed to improve efficiency and effectiveness in the operations (Kerzner, 2009). Second, the project intended to improve the client’s productivity in terms of quantity and quality (Kerzner, 2009). Third, it sought to streamline the production operations and monitoring process to advice for necessary alterations in the production (Kerzner, 2009). This meant that the implementing company maximises on the use of its resources. This was necessary and significant for the project’s success.

References

Kerzner, H. (2009). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. New York, NY: Wiley.

Schmidt, T. (2009). Strategic Project Management Made Simple: Practical Tools for Leaders and Teams. New York, NY: Wiley.

Cite this paper

Select style

Reference

StudyCorgi. (2021, February 21). Business Development Initiative for Success. https://studycorgi.com/business-development-initiative-for-success/

Work Cited

"Business Development Initiative for Success." StudyCorgi, 21 Feb. 2021, studycorgi.com/business-development-initiative-for-success/.

* Hyperlink the URL after pasting it to your document

References

StudyCorgi. (2021) 'Business Development Initiative for Success'. 21 February.

1. StudyCorgi. "Business Development Initiative for Success." February 21, 2021. https://studycorgi.com/business-development-initiative-for-success/.


Bibliography


StudyCorgi. "Business Development Initiative for Success." February 21, 2021. https://studycorgi.com/business-development-initiative-for-success/.

References

StudyCorgi. 2021. "Business Development Initiative for Success." February 21, 2021. https://studycorgi.com/business-development-initiative-for-success/.

This paper, “Business Development Initiative for Success”, was written and voluntary submitted to our free essay database by a straight-A student. Please ensure you properly reference the paper if you're using it to write your assignment.

Before publication, the StudyCorgi editorial team proofread and checked the paper to make sure it meets the highest standards in terms of grammar, punctuation, style, fact accuracy, copyright issues, and inclusive language. Last updated: .

If you are the author of this paper and no longer wish to have it published on StudyCorgi, request the removal. Please use the “Donate your paper” form to submit an essay.